Guadalajara Airport Terminal 2: progress and opening

November 6, 2026 · Newsroom

GAP reports progress of just over 10% on the new terminal. It is expected to open in the first quarter of 2029 and, with it, the airport would double its capacity.

Guadalajara Airport Terminal 2 is a little over 10% complete. The figure was announced on November 4 by Raúl Revuelta Musalem, CEO of Grupo Aeroportuario del Pacífico (GAP), the company that operates the airport. According to GAP’s schedule, construction would finish at the end of 2028 and the terminal would receive its first passengers in the first quarter of 2029.

In the meantime, nothing changes for those flying today. All flights still depart from and arrive at Terminal 1 of Guadalajara Airport.

What Terminal 2 is and how much it costs

It is a new building, separate from the current one. GAP now speaks of more than 109,000 square meters of floor space, which would be added to the 81,000 of Terminal 1. In the original announcement, from February 2025, the group had spoken of a 69,000-square-meter building. GAP has not explained the difference between the two figures.

The money comes from GAP’s 2025-2029 Master Development Program. For Guadalajara, that program includes almost 23 billion pesos (MXN), and not all of it is the terminal: the figure also includes new road access, another fire station and the purchase of land as a reserve for growth.

The design is by the firm of Spanish architect Carlos Lamela, who worked on Madrid-Barajas T4 and also has projects at Tijuana airport.

When it opens

The date GAP is working with is the first quarter of 2029. It is a target, not a confirmed opening date: with 10% of the work done at the end of 2026, there are still two years of construction left, and GAP has not said which airlines will operate in each building once both are running.

That is the question that will matter most to passengers in 2029, and for now it has no official answer.

What changes with the new terminal

The fundamental change is size. With Terminal 2, GAP estimates the airport will be able to handle more than 40 million passengers a year, double what it can handle today. For reference, 17.8 million people passed through Guadalajara in 2024.

What GAP has revealed about the building:

  • More counters, check-in kiosks and security checkpoints than in the current terminal.
  • Separate flows for departures and arrivals, each with its own bridge from the passenger drop-off area.
  • New systems to screen checked baggage and, according to the 2025 announcement, simplified customs inspection and automated immigration gates.
  • In a first stage, seven contact stands for aircraft (with jet bridges), according to what N+ reported.

A second access to the airport

Today the only way in is the Chapala highway, and at peak hours that shows. As part of the same project, GAP is building a viaduct of about 6 kilometers that will connect the airport with Adolf B. Horn avenue. That access will open together with Terminal 2, in 2029.

Inside the airport grounds, about 17 kilometers of hydraulic-concrete roads are already finished, according to GAP. For its part, the Jalisco government is widening and paving the central lanes of the Chapala highway.

Public transport also comes into the picture. GAP mentions lines 4 and 5 among the options to reach the area. Before choosing a route, check how public transport to the airport works today.

What it means for those flying from Guadalajara today

For now, not much. Check-in, security and lounges remain in the same place. What is advisable is to leave early: the Chapala highway has roadwork and traffic to the terminal may take longer than usual.

If you need to find your way inside the current building, the Guadalajara Airport map shows where counters, lounges and services are. To get there, the guide to transportation to Guadalajara Airport covers taxis, ride-hailing apps and buses.

Terminal 2 is the airport’s second major project in a short time. The previous one was the second runway at Guadalajara Airport, which is already in operation. We will update this article when GAP announces how airlines will be split between the two terminals.