Cargo at Guadalajara Airport totals 151,595 tonnes so far in 2026, 13.2% more than in the same period last year. With that figure, Guadalajara’s terminal is the third in the country by volume, behind only AIFA and AICM, and the one with the highest growth in total cargo among Mexican airports, according to Federal Civil Aviation Agency (AFAC) databases that Expansión reported on November 4.
The boost comes from industry. Jalisco manufactures electronic components for Foxconn, Intel and Nvidia, and those small, expensive parts travel by air.
| Cargo accumulated in 2026 | 151,595 tonnes |
| Annual growth | 13.2%, the highest in the country in total cargo |
| National ranking | 3rd, after AIFA and AICM |
| 2025-2029 master plan investment at GDL | More than 22 billion MXN (passengers and cargo) |
| New warehouse | 40% more storage capacity |
What moves through the airport
Raúl Revuelta, CEO of Grupo Aeroportuario del Pacífico (GAP), which operates the terminal, attributes much of the jump to demand for electronics linked to artificial intelligence. In the interview with Expansión he said the business is growing “at an impressive pace”.
It is not all chips. Air France has daily operations carrying berries, avocado, mango and meat products, and Korean Air Cargo and Lufthansa also move goods from Guadalajara. Perishables need speed and refrigeration, two things trucks cannot always guarantee on a long haul.
What is new is the automotive sector. For years, what arrived by air for carmakers was computers and high-value parts. According to Revuelta, components are now starting to arrive for the new production lines of Mazda and Nissan, which concentrated its manufacturing in Aguascalientes.
The cargo projects in GAP’s master plan
GAP’s 2025-2029 Master Development Program allocates more than 22 billion MXN to Guadalajara Airport, between passengers and cargo. For cargo it includes four new aprons where aircraft are parked and serviced.
There is another project not included in the plan. Guadalajara World Trade Center (GWTC), a cargo handling, storage and custody company in which GAP bought a 51.1% stake in mid-2024 for more than 875 million MXN, is building a warehouse that will increase the airport’s storage capacity by 40%.
On the passenger side, the most visible project is Guadalajara Airport Terminal 2, which is also part of the program.
The cost of growing
In its latest financial report, GAP reported that its bonded warehouse and cargo operations, businesses it runs directly, grew 20.7%. Spending rose too: 14.8% more on staff (84.7 million MXN), mainly from hiring operational workers at the airports and the bonded facility, and 13.1% more on security and insurance.
Those figures cover GAP’s whole network, not just Guadalajara. But this is where its largest cargo operation is.
One question remains. US trade policy is already forcing carmakers to rearrange their supply chains, and Revuelta sees it as an opportunity for the airport. The close of 2026 will show how much weight each side carries.